San Diego Zoo Safari Park

Jauregui & Culver, Inc. installed an above ground diesel storage tank (AST) for the Wild Animal Park (which is now the San Diego Zoo Safari park.)  Jauregui & Culver, Inc. procured permits, poured the slab and put in the tank. We continue to service and provide regulatory compliance testing for the tank.

 

 

 

COC Fuel Facility

Jauregui & Culver, Inc. did a full design build for the County of San Diego Operation’s fuel facility. We procured permits, installed tanks, canopy, and a fuel system. We custom built the shoring that went in on the sides of the tank hole. The concrete footings, tank slab, and drive slabs were poured. Jauregui & Culver, Inc. also installed the fuel management system and continues to provide service and testing for the station. The existing fuel site was demolished, and can be seen here.

In addition, Jauregui & Culver, Inc. provided piping for the emergency generator system and is continuing to design build for the emergency generator system and other projects at this facility.

 

 

 

 

Sam’s Club Bakersfield #4819

Sam’s Club #4819 Bakersfield was a ground up fuel station. Jauregui & Culver, inc. excavated and installed two 20,000 gallon 87 gasoline and one 20,000 gallon split 12,000/8,000 10′ diameter Xerxes Underground Storage Tanks (UST) and deadmen.

We installed Fiberglass, APT, and steel piping to compile the fueling system, including trenching and gravel backfill. Two 3+1 gas/diesel dispensers and four 3+0 gas dispensers were installed, including the Under Dispenser Containment (UDC) basins, dispenser hanging hardware, and dispenser valance. Brine and vacuum tubing for the Veeder Root continuous monitoring and Pressure and Flow sensors in dispenser for the In Station Diagnostics (ISD). The Healy Clean Air Separator (CAS) was installed as part of the EVR II system.

We provided required Enhanced Leak Detection (ELD) testing of the fuel system at the conclusion of the installation of the fueling system and prior to opening. All fuel lines were purged and the dispensers calibrated, completing this project.

LPL San Diego Tower

Jauregui & Culver, Inc. procured permits for and installed a 4,000 gallon Above-ground Storage Tank (AST) for diesel and double wall steel fuel piping.  We furnished and installed AST remote fill assembly, fuel filtration unit, fuel management control panel, Duplex pump system, and tank monitoring system, including all low voltage electrical wiring and conduit.

 

 

Jet Air Tank Removal

Jauregui & Culver, Inc. removed two single wall 12,000 gallon tanks enclosed in a concrete vault.  Demolition and environmental remediation were provided.

 

 

 

 

 

 

Scripps Memorial Hospital Tank Installation

Watch as our team flawlessly installs this UST at Scripps Memorial Hospital.

 

Pala Mini Mart Dispenser Replacement

Jauregui & Culver, Inc. furnished and installed new dispensers for the Pala Casino Mini Mart. We also fabricated and installed a column style canopy extension which including engineer drawings and structural calculations.

 

 

 

Pala Mini Mart Re-Pipe

Jauregui & Culver, Inc. replaced the fuel piping for the Pala Mini-Mart.  We phased the work so that at least one row of dispensers was operational during construction.  We purged the fuel in the existing below ground piping back into the underground storage tanks (USTs) with pressurized nitrogen.  The existing piping was abandoned in place after the fuel was removed.

We sawcut and removed the existing concrete and asphalt surfaces between the USTs and the dispensers as needed for the installation of the double wall fiber glass piping.  We dug pipe trenches and gravel bedding materials required by the pipe manufacturer and to meet industry standards.

We performed pressure tests to all the new piping per industry standards.  We purged the fuel into the new piping system and tested for proper operation, calibrated the dispensers, and replaced all dispenser fuel filters.

 

 

Fallbrook Village Aviation UST Removal

Two unknown tanks were discovered during development of this property. Jauregui & Culver removed two single-wall steel underground storage tanks approximated at 4,000 gallons each.

We furnished the San Diego Country Department of Environmental Health (DEH) and Fallbrook Fire Department UST Removal permits, including permit fees, permit application preparation, submission, and pick up.  A one time California State EPA number was obtained as required for manifesting and disposal purposes. We washed the UST’s and degas as required by agency guidelines.

The UST’s and all wash stream was manifested and lawfully disposed of. Soil samples were taken and analyzed. Jauregui & Culver, Inc. will back-fill with material equal to the volume of the removed UST’s and back-fill the tank hole to subgrade.

 

 

 

University of San Diego Tank Removal

 

 

 

 

 
Jauregui & Culver, Inc. removed a 10,000 gallon underground storage tank from beneath one of the campus roadways.  We furnished permits, testing, and environmental remediation.  Additionally, the soil around the tank was found to be contaminated.  Jauregui & Culver removed and disposed of the contaminated soil overburden in accordance to the county’s regulations.